CLARK COUNTY WATER RECLAMATION DISTRICT

 

PROPOSED BID OPPORTUNITIES
(Construction)

 Legend: PWP - Public Works Project
                BID - Construction / Repairs

 

CONSTRUCTION FROM JANUARY 2012 THRU MARCH 2014

 Number

 Type

Description

Award Date*

Estimated Cost**

667 PWP 100 kW Photovoltaic System  January 5, 2012 $600,000
621 PO2  PWP Central Plant Corrosion Management Plan  February 7, 2012 $6,400,000
653 PWP Central Plant ERW Pump Station February 7, 2012 $1,100,000
659 PWP Facilities Roof Rehabilitation / Replacement March 6, 2012 $600,000
664 PWP Blue Diamond Ponds Rehabilitation February 7, 2012 $500,000
653 PWP Central Plant 66-inch Force Main Rehabilitation April 3, 2012 $5,500,000
661 PWP Las Vegas Valley Manhole and Pipe Rehabilitation - Package 3 June 5, 2012 $5,700,000
662 PWP AWT Stormwater Containment June 5, 2012 $1,400,000
663 PWP Lincoln Lift Station Modifications June 5, 2012 $600,000
647 PWP Maryland Parkway Lift Station Decommissioning July 3, 2012 $2,400,000
583 PWP Enterprise Facility July 3, 2012 $14,200,000
511D PWP Las Vegas Wash Channelization Improvements August 7, 2012 $31,000,000
655 PWP Laughlin Lift Station No. 2 Force Main Rehabilitation August 7, 2012 $13,000,000
646 PO2 PWP Central Plant Perimeter, Lighting, & Pavement Management September 4, 2012 $2,800,000
660 PWP CSS Construction Yard Improvements November 6, 2012 $1,100,000
656 PWP Central Plant Membranes - Phase 2 Design Build - RFFP and Final Proposal November 20, 2012 $112,500,000
560A PO5 PWP Moapa Valley Water Main & Fiber Optic Communications Lines December 4, 2012 $4,900,000
560A PO3 PWP Moapa Valley Force Main December 4, 2012 $5,800,000
585 PO2  PWP Searchlight Collection System & Groundwater Recharge Assessment  December 4, 2012 $2,000,000
560A PO2 PWP Moapa Valley Lift Station  December 4, 2012 $5,500,000
TBD149 PWP Power Monitoring  December 4, 2012 $200,000
TBD119 PWP Central Plant Multi-Mode Fiber  February 5, 2013 $660,000
TBD148 PWP Truck Wash Facility February 5, 2013 $250,000
TBD076  PWP Las Vegas Valley Manhole & Pipe Rehabilitation - Package 4 March 7, 2013 $1,900,000
TBD154 PWP New Fire and Life Safety Monitoring System  June 4, 2013 $2,400,000
TBD078  PWP Las Vegas Valley Manhole & Pipe Rehabilitation - Package 6  June 4, 2013 $5,200,000
TBD145  PWP Moapa Valley Manhole & Pipe Rehabilitation  July 2, 2013 $4,500,000
TBD077  PWP Las Vegas Valley Manhole & Pipe Rehabilitation - Package 5  July 2, 2013  $4,200,000
TBD126  PWP Dissolved Air Flotation Thickener No. 1-4 Rehabilitation  July 2, 2013 $270,000
TBD135  PWP Central Plant Building Renovations  August 6, 2013 $19,400,000
TBD059  PWP AWT Laboratory Renovations  August 6, 2013 $7,600,000
668 PWP Paradise-Whitney Interceptor - Package 1  August 6, 2013 $36,800,000
585 PO1  PWP Searchlight Water Resource Center  August 6, 2013 $10,000,000
665 PWP AWT Clarifier Rehabilitation/Existing Facilities Structural Evaluation  September 3, 2013 $2,700,000
669 PWP Paradise-Whitney Interceptor-Package 2  December 13, 2013 $35,500,000
640 PWP Laughlin Lift Station No. 2 Rehabilitation  March 4, 2014 $3,700,000
670 PWP Paradise - Whitney Interceptor - Package 3 July 1, 2014 $59,000,000
TBD079 PWP Las Vegas Valley Manhole & Pipe Rehabilitation - Package 7 July 1, 2014 $3,100,000
TBD118 PWP Radio Towers February 3, 2015 $450,000
TBD156 PWP Moapa Valley Manhole & Pipe Rehabilitation March 3, 2015 $12,500,000


.
For any additional details please contact Contracts at 702-668-8143.
Click here for Active Bid Opportunities
Click here for Bids Pending Board Approval
Click here for Bids Awarded
Click here to return to Bid Opportunities Home Page


*Award Date is a proposed date only and is subject to change.

**The costs being provided are considered as estimates only and are not to be considered as a bench mark in formulating costs for any project.